Honey Creek OEPA 319 Stream Restoration
Project 2007-2010
The Project and
Funding
The Honey
Creek Watershed Association was awarded an Ohio Environmental Protection Agency
319 Stream Restoration Grant to restore a degraded section of the Honey
Creek. We had many partners that also
helped make this project possible by providing a local match of 40% of the
grant. Our partners included the Miami
Soil and Water Conservation District, Miami County Park District, Honey Creek
Watershed Association’s Board of Directors, Tri-Cities North Regional
Wastewater Authority, Veolia Water North America, City of Tipp City, City of
The completion of this project improved water quality by reducing, per year, an estimated 41.4 tons of
sediment, 82.7 lbs of nitrogen and 41.4 lbs of phosphorus from entering into
the Honey Creek. These reductions in
nutrients from neighboring fields and sediment loadings will also enhance the
aquatic habitat, inviting more diverse and higher quality fish such as the
River Chub and the Scarlet Shiner that have been spotted in other sections of
the Honey Creek.
Construction
We hired
KCI Technologies Inc, from
Most of the
construction was performed in the winter and the four acres of new habitat were
planted in the spring. Installing sediment
control features was the first part of the job. Silt fences were installed around
all pile of materials that were pulled out of the stream to prevent it (mostly
soil) from washing back in to the stream.
A spoilage area was installed for the heavy equipment to remove their
excess mud. It is important to have sediment control features to prevent as much
sediment from entering the stream during construction as possible. Our next step was clearing out three log
jams that were causing the stream to erode itself in certain areas. We began to lay back some of the banks in
preparation for their stabilization features.
The
techniques and structures used included two 15+foot rock cross
vanes and one 10+foot j-hook, both of which redirect the main current (and
eroding power of the stream), one 75ft live lift that helps defuse the stream’s
energy for normal flow, the creation of two spillways for release of
floodwaters for high flow further reducing erosion, and regrading and
re-vegetation (using live Willow tree cuttings) of the bank slopes along
project area.
For any questions regarding this
project, please contact the
Honey Creek watershed Assoc
937-667-7878
STREAMBANK RESTORATION PROJECT PICTURES
PRE TO POST
CONSTRUCTION PICTURES
DECEMBER 16, 2008
DECEMBER 17, 2008
DECEMBER 18, 2008
DECEMBER 31, 2008
JANUARY 5, 2009
JANUARY 6, 2009
JANUARY 7, 2009
MARCH 16,
2009
JUNE 6, 2009